(308) 324-2386

[su_table]

Distribution – aging

Miles

Dollars

Underground aging projects $397,500
South of Lexington on Road 749 5.00 $375,000
Northeast of Kearney 3.50 $225,574
North of Hershey along Wildlife Road 5.00 $200,000
Northeast of Eddyville on Buzzard’s Roost 2.00 $150,000
Southeast of Ravenna along Gibbon Road 2.00 $140,000
Underground aging projects (2016 carryover) 1.50 $100,000
Northeast of Lexington on Road 439 1.00 $80,000
Johnson Lake Drive $35,000
Hockley Subdivision northwest of Cozad 0.86 $34,015
North of Ravenna 0.50 $34,015
Southeast Johnson Lake on Lane 1 0.25 $28,125
Total 19.61 miles $1,828,729

Distribution – upgrades

Miles

Dollars

South of Lexington 10.00 $800,000
Sumner to Overton on Road 444 2.03 $486,773
KAAPA Ethanol to substation west of Ravenna 5.00 $400,000
Hershey voltage conversion $250,000
West of Ravenna on Keystone Road 2.00 $160,000
North of Gothenburg to North of Willow Island 2.00 $145,596
Brady circuit balancing 1.00 $80,000
Line to southeast Elm Creek substation 1.00 $80,000
South of Overton 1.00 $80,000
West of Overton 1.00 $80,000
Total 30.03 miles $2,962,369

Transmission line & substation upgrades

Miles

Dollars

Overton to Elm Creek 9.50 $2,000,000
Johnson Lake substation $1,000,000
Sumner substation $1,000,000
Transmission line to Sumner substation 4.00 $860,000
Bailey Yard transmission switches $100,000
Substation northwest of Shelton $100,000
Substation northeast of Gibbon $80,000
Hershey substation 1 retirement $10,000
Hershey substation 2 retirement $10,000
Total 13.50 miles $5,160,000

GRAND TOTAL

63.14 miles

$9,951,098

 
[/su_table]
Almost $10 million in system improvements are scheduled for construction in 2017. As a not-for-profit utility, Dawson PPD budgets to reinvest in its system annually to ensure reliable and safe electricity.
“Dawson PPD is always evaluating its electrical system to determine areas that need upgrades or new equipment to benefit customers,” said Manager of Operations Jeremy Kaiser. “Taking a proactive approach ensures that Dawson PPD is continuously improving service reliability for its customers and safety for all.”
The budget was approved at the December board meeting. Project funding is derived from previous annual sales and long-term bonds. All projects are evaluated on safety, reliability and system loading.
Construction projects are divided into three categories:

  1. Aging distribution replacement
    • These power lines carry electricity to customer homes, farms and businesses.  Aging distribution describes power lines that have been in place for more than 50 years, including original equipment from the early 1940s. These lines are in need of complete replacement to ensure safety and reliability. Between 20 to 30 miles are budgeted to be replaced each year.
  2. Distribution upgrades
    • This includes projects scheduled as part of a multi-year plan.  The plan divides large projects into smaller, more manageable parts.
  3. Transmission line & substation upgrades
    • The third category represents Dawson PPD’s need to increase its capacity for power at substations and on distribution and transmission lines.  Transmission lines carry power between substations.  A substation is a point where electricity is sent into the distribution system so it can be delivered to customers.

 
January 2017

Translate »