Dawson PPD 2023 work plan

About $6.1 million in electric distribution system improvements is budgeted for 2023. The plans will improve roughly 50 miles of power lines.

As a not-for-profit utility, Dawson PPD reinvests in its system annually to ensure safe and reliable electricity.
The budget was approved at the December board meeting. Project funding is derived from previous annual sales and long-term bonds. All projects are evaluated on safety, reliability and system loading.

Construction projects are divided into three categories:

Aging distribution replacement

These power lines carry electricity to customer homes, farms and businesses. Aging distribution describes power lines that have been in place for more than 50 years, including original equipment from the early 1940s. These lines are in need of complete replacement to ensure safety and reliability. Between 20 to 30 miles are budgeted to be replaced each year.

Distribution upgrades

These power lines are located on the side of the road and provide power to homes, farms and businesses. The plans include projects scheduled as part of a multi-year plan and divides large projects into smaller, more manageable parts.

Transmission line & substation upgrades

The third category represents Dawson PPD’s need to increase its capacity for power at substations and on distribution and transmission lines. Transmission lines carry power between substations. A substation is a point where electricity is sent into the distribution system so it can be delivered to customers.

OTHER NEWS

Working with birds of prey

Working with birds of prey

When you think about hunting, you may imagine a person with a shotgun and his trusty dog by his side. Or, perhaps, an individual high in a tree stand with their bow. But what about an individual who hunts with a hawk? Falconry is the art of hunting with raptors like...

read more
Between the lines: Is retail choice right for Nebraska?

Between the lines: Is retail choice right for Nebraska?

By Gwen Kautz, Dawson PPD General Manager gkautz (at) dawsonpower.com 308-324-2386 Over the holidays, a report was published that claimed Nebraskan’s are not benefiting from the public power model in Nebraska and that introducing competition would garner lower rates....

read more
Celebrating 80 years of service

Celebrating 80 years of service

On January 25, 1937, local farmers and other community leaders filed a petition with the Nebraska Department of Roads and Irrigation for the creation of Dawson County Public Power District. The District was officially formed February 26, 1937. The District put its...

read more
Translate »