About $8.2 million in electric distribution system improvements is budgeted for 2024. The plans will improve roughly 55 miles of power lines.
As a not-for-profit utility, Dawson PPD reinvests in its system to ensure safe and reliable electricity.
The budget was approved at the November board meeting. Project funding is derived from previous annual sales and long-term bonds. All projects are evaluated on safety, reliability and system loading.
Affected customers are contacted by Dawson PPD to communicate any necessary power outages or property access needed to complete the work.
Construction projects are divided into three categories:
Distribution upgrades (Site Specific)
These power lines are located on the side of the road and provide power to homes, farms and businesses. The plans include projects scheduled as part of a multi-year plan and divides large projects into smaller, more manageable parts.
Aging distribution replacement
These power lines carry electricity to customer homes, farms and businesses. Aging distribution describes power lines that have been in place for more than 50 years, including original equipment from the early 1940s. These lines are in need of complete replacement to ensure safety and reliability. Between 20 to 30 miles are budgeted to be replaced each year.
Transmission line & substation upgrades
The third category represents Dawson PPD’s need to increase its capacity for power at substations and on distribution and transmission lines. Transmission lines carry power between substations. A substation is a point where electricity is sent into the distribution system so it can be delivered to customers.
OTHER NEWS
Employees hired from within
Sara Campbell, Bob Miller, Trever Miller and Casandra Way were recently promoted from within.
Take action against scams
Each year, Nebraskans are subject to a variety of consumer scams. Everyone, regardless of age, sex, nationality, education level or financial status is a target for a consumer scam.
Strong and steady: A look at Dawson PPD’s 2021 financials
The Dawson PPD Board of Directors set some key goals for 2021 and beyond, including the establishment of a Rate Stabilization Fund. The Rate Stabilization Fund will be deposited into or withdrawn from accordingly to help balance the surplus years of revenue from insufficient years.