About $8.2 million in electric distribution system improvements is budgeted for 2024. The plans will improve roughly 55 miles of power lines.

As a not-for-profit utility, Dawson PPD reinvests in its system to ensure safe and reliable electricity.

The budget was approved at the November board meeting. Project funding is derived from previous annual sales and long-term bonds. All projects are evaluated on safety, reliability and system loading.

Affected customers are contacted by Dawson PPD to communicate any necessary power outages or property access needed to complete the work.

Construction projects are divided into three categories:

Renewable energy infographic

Distribution upgrades (Site Specific)

These power lines are located on the side of the road and provide power to homes, farms and businesses. The plans include projects scheduled as part of a multi-year plan and divides large projects into smaller, more manageable parts.

Aging distribution replacement

These power lines carry electricity to customer homes, farms and businesses. Aging distribution describes power lines that have been in place for more than 50 years, including original equipment from the early 1940s. These lines are in need of complete replacement to ensure safety and reliability. Between 20 to 30 miles are budgeted to be replaced each year.

Transmission line & substation upgrades

The third category represents Dawson PPD’s need to increase its capacity for power at substations and on distribution and transmission lines. Transmission lines carry power between substations. A substation is a point where electricity is sent into the distribution system so it can be delivered to customers.

OTHER NEWS

Monster trucks spotted at Dawson PPD

Monster trucks spotted at Dawson PPD

New construction crew foremen trucks have arrived at Dawson PPD, and they're a bit monstrous. The commercial-grade CV International trucks are listed as medium duty with a gross vehicle weight rating of 23,500 lbs. Dawson PPD crew foremen previously drove a Dodge Ram...

read more

Contact us when planning for new construction

Building a new structure for your home or business takes a lot of planning. As you are working through your budget, please be sure to contact Dawson PPD for a quote on the cost to bring electrical power to your location. Dawson PPD’s policy, implemented in February...

read more
Translate »