We’re committed to delivering reliable electricity to you. That’s why we recently replaced a transmission line switch that had reached its service limit. While the original switch served us well for 40+ years, proactive maintenance identified the need for an upgrade.
These switches play a vital role in our power grid. They allow us to reroute electricity for faster restoration during widespread outages and ensure the safety of our lineworkers during maintenance on sub-transmission lines.
Dawson PPD’s investment in a new 90-foot digger derrick proved to be instrumental in this project. Originally scheduled for a specific date, we were able to reschedule the switch replacement to avoid impacting irrigation customers who needed to water their crops.
This flexibility not only benefits our customers but also translates to cost savings for Dawson PPD. By utilizing our own equipment and skilled crew, we eliminated the need to hire an external crane company for the switch installation.
We are dedicated to maintaining a reliable and efficient power grid by investing in infrastructure and equipment to deliver the exceptional service you depend on.
OTHER NEWS
Between the lines: Customer service
Good customer service is essential for any company that wants to succeed today.
CNPPID and Dawson PPD plan to refile merger petition with Nebraska Power Review Board
The Nebraska Power Review Board has held that it cannot approve the merger petition between The Central Nebraska Public Power and Irrigation District and Dawson Public Power District based on a technical issue in the charter documents.
Dawson PPD partners with NEF to secure $15 million USDA grant
Dawson Public Power District is pleased to partner with the Nebraska Enterprise Fund on launching a new $15 million loan fund to support meat and poultry processing. The U.S. Department of Agriculture recently awarded a $15 million grant to NEF to support the...