About $6.1 million in electric distribution system improvements is budgeted for 2023. The plans will improve roughly 50 miles of power lines.
As a not-for-profit utility, Dawson PPD reinvests in its system annually to ensure safe and reliable electricity.
The budget was approved at the December board meeting. Project funding is derived from previous annual sales and long-term bonds. All projects are evaluated on safety, reliability and system loading.
Construction projects are divided into three categories:
Aging distribution replacement
These power lines carry electricity to customer homes, farms and businesses. Aging distribution describes power lines that have been in place for more than 50 years, including original equipment from the early 1940s. These lines are in need of complete replacement to ensure safety and reliability. Between 20 to 30 miles are budgeted to be replaced each year.
Distribution upgrades
These power lines are located on the side of the road and provide power to homes, farms and businesses. The plans include projects scheduled as part of a multi-year plan and divides large projects into smaller, more manageable parts.
Transmission line & substation upgrades
The third category represents Dawson PPD’s need to increase its capacity for power at substations and on distribution and transmission lines. Transmission lines carry power between substations. A substation is a point where electricity is sent into the distribution system so it can be delivered to customers.
OTHER NEWS
CNPPID and Dawson PPD plan to refile merger petition with Nebraska Power Review Board
The Nebraska Power Review Board has held that it cannot approve the merger petition between The Central Nebraska Public Power and Irrigation District and Dawson Public Power District based on a technical issue in the charter documents.
Dawson PPD partners with NEF to secure $15 million USDA grant
Dawson Public Power District is pleased to partner with the Nebraska Enterprise Fund on launching a new $15 million loan fund to support meat and poultry processing. The U.S. Department of Agriculture recently awarded a $15 million grant to NEF to support the...
Laguna-Gutierrez receives $2,000 Dawson PPD Utility Line Scholarship
Dawson Public Power District has awarded Juan Laguna-Gutierrez a $2,000 utility line scholarship to pursue his degree. Laguna-Gutierrez is a student at Lexington High School and is the son of Juan Laguna-Sanchez and Alejandra Gutierrez-Alvarado.