About $6.1 million in electric distribution system improvements is budgeted for 2023. The plans will improve roughly 50 miles of power lines.
As a not-for-profit utility, Dawson PPD reinvests in its system annually to ensure safe and reliable electricity.
The budget was approved at the December board meeting. Project funding is derived from previous annual sales and long-term bonds. All projects are evaluated on safety, reliability and system loading.
Construction projects are divided into three categories:
Aging distribution replacement
These power lines carry electricity to customer homes, farms and businesses. Aging distribution describes power lines that have been in place for more than 50 years, including original equipment from the early 1940s. These lines are in need of complete replacement to ensure safety and reliability. Between 20 to 30 miles are budgeted to be replaced each year.
Distribution upgrades
These power lines are located on the side of the road and provide power to homes, farms and businesses. The plans include projects scheduled as part of a multi-year plan and divides large projects into smaller, more manageable parts.
Transmission line & substation upgrades
The third category represents Dawson PPD’s need to increase its capacity for power at substations and on distribution and transmission lines. Transmission lines carry power between substations. A substation is a point where electricity is sent into the distribution system so it can be delivered to customers.
OTHER NEWS
Wulf awarded $2,000 Dawson PPD STEM Scholarship
Kearney native Hayden Wulf has been awarded a $2,000 STEM Scholarship from Dawson Public Power District. Wulf is the daughter of Douglas and Kellie Wulf. She is currently studying Civil Engineering at the University of Nebraska-Lincoln.
April 10 is National Lineworker Appreciation Day
Celebrate the power behind your power. This Lineworker Appreciation Day, Dawson PPD invites our customers to recognize our local line crews and all utility lineworkers across America. Our lineworkers’ top priority is ensuring that we have reliable electricity for everyday life. Got power? Thank a lineworker!
Camp Comeca welcomes Youth Energy Leadership Camp after forest fire
Within a month of the fire, the NREA settled on Camp Comeca as its new host in 2023.