(308) 324-2386
Dawson PPD 2023 work plan

About $6.1 million in electric distribution system improvements is budgeted for 2023. The plans will improve roughly 50 miles of power lines.

As a not-for-profit utility, Dawson PPD reinvests in its system annually to ensure safe and reliable electricity.
The budget was approved at the December board meeting. Project funding is derived from previous annual sales and long-term bonds. All projects are evaluated on safety, reliability and system loading.

Construction projects are divided into three categories:

Aging distribution replacement

These power lines carry electricity to customer homes, farms and businesses. Aging distribution describes power lines that have been in place for more than 50 years, including original equipment from the early 1940s. These lines are in need of complete replacement to ensure safety and reliability. Between 20 to 30 miles are budgeted to be replaced each year.

Distribution upgrades

These power lines are located on the side of the road and provide power to homes, farms and businesses. The plans include projects scheduled as part of a multi-year plan and divides large projects into smaller, more manageable parts.

Transmission line & substation upgrades

The third category represents Dawson PPD’s need to increase its capacity for power at substations and on distribution and transmission lines. Transmission lines carry power between substations. A substation is a point where electricity is sent into the distribution system so it can be delivered to customers.

OTHER NEWS

Take action against scams

Take action against scams

Each year, Nebraskans are subject to a variety of consumer scams. Everyone, regardless of age, sex, nationality, education level or financial status is a target for a consumer scam.

read more
Strong and steady: A look at Dawson PPD’s 2021 financials

Strong and steady: A look at Dawson PPD’s 2021 financials

The Dawson PPD Board of Directors set some key goals for 2021 and beyond, including the establishment of a Rate Stabilization Fund. The Rate Stabilization Fund will be deposited into or withdrawn from accordingly to help balance the surplus years of revenue from insufficient years.

read more
Whose line is it, anyway?

Whose line is it, anyway?

When it comes to power lines and equipment, it is not always obvious if it is the customer's property or Dawson PPD's. These four illustrations depict some of the most common scenarios within our service territory. Remember that 811 Digger's Hotline only locates...

read more
Translate »