Dawson PPD 2023 work plan

About $6.1 million in electric distribution system improvements is budgeted for 2023. The plans will improve roughly 50 miles of power lines.

As a not-for-profit utility, Dawson PPD reinvests in its system annually to ensure safe and reliable electricity.
The budget was approved at the December board meeting. Project funding is derived from previous annual sales and long-term bonds. All projects are evaluated on safety, reliability and system loading.

Construction projects are divided into three categories:

Aging distribution replacement

These power lines carry electricity to customer homes, farms and businesses. Aging distribution describes power lines that have been in place for more than 50 years, including original equipment from the early 1940s. These lines are in need of complete replacement to ensure safety and reliability. Between 20 to 30 miles are budgeted to be replaced each year.

Distribution upgrades

These power lines are located on the side of the road and provide power to homes, farms and businesses. The plans include projects scheduled as part of a multi-year plan and divides large projects into smaller, more manageable parts.

Transmission line & substation upgrades

The third category represents Dawson PPD’s need to increase its capacity for power at substations and on distribution and transmission lines. Transmission lines carry power between substations. A substation is a point where electricity is sent into the distribution system so it can be delivered to customers.

OTHER NEWS

Boring machine is anything but

Boring machine is anything but

  It’s big. It’s powerful. And it virtually leaves yards undisturbed. Dawson PPD recently invested in an underground boring machine to assist with line construction. The plan is to bore power lines underground when they cross major roads and intersections. This...

read more
How Santa saves energy

How Santa saves energy

How Santa saves energy Santa leaves his decorations up year-round, so he uses LED holiday light strands. LED holiday strands can last up to 40 seasons, which make them a great option for any festive home. Santa requires several power tools to make a year's worth of...

read more

Policy update to service fees

At the October Board Meeting, an update was passed on the Customer Policy 213: Listing of Current Charges. Some key changes: Meter reading charge - $55 Non-payment reconnect during business hours - $100 Non-payment reconnect after business hours - $150 Returned...

read more
Translate »