Dawson PPD begins sub-transmission line reconstruction

(January 3, 2017) Lexington, Neb. – Dawson Public Power District has begun reconstructing a sub-transmission line between Overton and Elm Creek. The $2 million project is expected to be complete by June 1, 2017. This is the first of three projects Dawson PPD has...
Save money and energy through the  EnergyWise Program

Save money and energy through the EnergyWise Program

If your New Year’s resolution is to be more energy efficient, Dawson PPD may have a rebate for you. Known as the EnergyWiseSM Program, customers are rewarded with incentives for making energy efficient improvements within their homes. The program is offered in...
Dawson PPD 2017 planned upgrades

Dawson PPD 2017 planned upgrades

[su_table] Distribution – aging Miles Dollars Underground aging projects – $397,500 South of Lexington on Road 749 5.00 $375,000 Northeast of Kearney 3.50 $225,574 North of Hershey along Wildlife Road 5.00 $200,000 Northeast of Eddyville on Buzzard’s Roost...
Between the lines: Reflections of the ice storms

Between the lines: Reflections of the ice storms

By Gwen Kautz, Dawson PPD General Manager gkautz (at) dawsonpower.com 308-324-2386 It’s hard to believe those two ice storms happened 10 years ago. So many memories came flooding back as we prepared to write the story. In the flurry of long days and nights, I wondered...